Rathgeber Natural Resource Park

Park Plans

The adopted vision, anticipated design sequence and source-backed funding information.

Last substantive update: August 15, 2026

Independent community website. Confirm park access, schedules and conditions through official City sources.

The Dripping Springs City Council approved the Rathgeber Natural Resource Park Vision Plan on September 3, 2024. The plan establishes the intended character and long-range direction of the park. It is not the same as a final set of construction drawings.

Official sources: Vision-plan approval staff report · Official City park page

What the vision plan does

The City’s planning scope included site analysis and data collection, public and stakeholder engagement, needs assessment, operations and land-management strategies, and budget and funding strategies. That work created a framework for protecting the property and developing visitor experiences in phases.

The adopted direction emphasizes a nature-focused park with low-impact recreation and education. Concepts publicly associated with the plan include trails, birding and wildlife viewing, a nature center, nature education and stargazing.

What remains to be designed

  • Final trail alignments, lengths, surfaces and accessibility treatments.
  • Public entrance and emergency-access locations.
  • Parking capacity, circulation and any phasing of parking improvements.
  • The size, location and program of any nature center or support building.
  • Utilities, drainage, environmental permitting and other regulatory requirements.
  • Operating hours, visitor rules, reservations and maintenance practices.
Publishing rule: Until the City approves detailed plans, maps and amenities should be labeled conceptual and should not be presented as promised improvements.

Anticipated project sequence

  1. Schematic design translates the adopted vision into a more defined Phase I concept.
  2. Survey, geotechnical and environmental information supports engineering and site decisions.
  3. Design development and construction documents establish buildable details.
  4. Permitting and regulatory reviews address applicable requirements.
  5. Bidding and contract award occur after the City authorizes a construction package.
  6. Construction, inspection and closeout precede any public opening.

Official sources: 2024 next-steps staff report · FY2027 departmental budget proposal

Funding

Hays County has allocated $3.55 million from the 2020 Parks and Open Space Bond for future Rathgeber improvements. The September 2024 funding agreement identified an initial $695,150 for construction plans as reimbursable. A later FY2027 departmental budget proposal listed an estimated $721,000 for Phase I schematic design, survey and geotechnical work, construction documents, permitting and regulatory coordination.

Earlier POSAC materials show a $7.5 million project funding request. That request should not be presented as the current budget, final project cost or amount awarded. Scope, estimates, available funds and phasing can change.

Official sources: Hays County project page · 2024 funding agreement · FY2027 departmental budget proposal · POSAC recommendations

Current planning signal

The City’s FY2027–FY2031 strategic business plan identifies RNRP Design Phase I in FY2027 and RNRP Construction of Phase I in FY2028. The same document states that projects are continually reevaluated and approved through the annual budget process. These entries are useful milestones to watch, but they are not a guaranteed opening schedule.